Long‑term investment programme

Parameters of the Company’s Long‑Term Investment Programme for 2024–2027Plans for the long-term investment programme of Rosseti Kuban, PJSC were approved by Order No. 5@ of the Ministry of Energy of Russia dated 16 November 2023.
Indicator 2021 2022 2023 2024 (plan) 2025 (plan) 2026 (plan) 2027 (plan)
Amount of financing (RUB mln) 7,215 12,076 18,235 20,155 8,676 7,688 8,238
Capital investment utilisation (RUB mln) 5,871 11,469 12,579 17,418 6,733 6,783 7,144
Commissioning as a part of fixed assets (RUB mln) 5,128 8,634 11,960 17,498 12,006 5,709 8,848
Commissioning as a part of transformer capacities (MVA) 220 579 606 354 339 266 496
Commissioning as a part of power transmission lines (km) 612 1,069 1,052 1,319 832 776 771